Process 22 of 40 — PMBOK 8

Monitor and Control Finances

What Control Costs became in PMBOK 8: revenue now appears in the forecasts, and funding proposals are a new output of the process.

Performance Domain Finance Focus Area Monitoring and Controlling

Monitor and Control Finances is the process that tracks the project’s money while the work runs: comparing actual spending with the cost baseline, forecasting where costs will end up, and raising change requests when the numbers drift.

What changed in Monitor and Control Finances: the Sixth Edition's Control Costs compared with the Eighth Edition
Control Costs in the Sixth Edition, Monitor and Control Finances in the Eighth: the main changes at a glance. The full analysis follows.

What changed

This is Control Costs under a new name, and the name is wider in two ways. “Monitor and” matches the other monitoring processes in the edition, such as Monitor and Control Project Performance. “Finances” replaces “Costs” in the same way that Plan Financial Management replaced Plan Cost Management.

The outputs show the wider scope

The output list grew from five entries to six, and two of them show the change:

  • Revenue and cost forecasts replace the Sixth Edition’s cost forecasts. The process now looks at money coming in as well as money going out.
  • Funding proposals are new. When the forecast shows the project will need more money, or money at a different time, this process now produces the proposal for it.

Work performance information, change requests and plan and document updates are still outputs, as before.

The input list went from five entries to four, but nothing was lost. Project funding requirements, which the previous set listed as an input of its own, now sits under project documents.

The tools did not change

The tools are the same four: expert judgment, data analysis, the to-complete performance index, and the project management information system. Earned value analysis, trend analysis and reserve analysis are still listed under data analysis.

If you learned the previous set

Earned value is still at the center of this process, so keep the formulas: cost and schedule variance, CPI and SPI, estimate at completion and TCPI. What is new is the idea that controlling a project’s finances includes its revenue and its funding, not only its spending.

To practise the formulas on your own numbers, use the earned value calculator. It shows every result with the working, including all four EAC formulas and both versions of TCPI.

Inputs, Tools & Techniques, and Outputs

Compared with the Sixth Edition’s Control Costs. Items marked New, Renamed or Moved changed; everything else carries over.

Inputs 4

  • Project management plan
  • Project documents
  • Work performance data
  • Organizational process assets

Now under project documents: Project funding requirements

Tools & Techniques 4

  • Expert judgment
  • Data analysis
  • To-complete performance index
  • Project management information system

Outputs 6

  • Work performance information
  • Revenue and cost forecasts RenamedWas cost forecasts
  • Change requests
  • Funding proposals New
  • Project management plan updates
  • Project document updates

Every ITTO column in the eighth edition ends in “Etc.”, so the guide presents these lists as typical, not complete. Grouped items such as project documents are shown at the top level. PMBOK® Guide — Eighth Edition, §2.4.2.4. What changed in the ITTOs, across all 40 processes.

← All PMBOK 8 Processes