Process 19 of 40 — PMBOK 8

Plan Financial Management

What Plan Cost Management became in PMBOK 8: why "Cost" became "Financial", and the funding strategy that is now an output of the process.

Performance Domain Finance Focus Area Planning

Plan Financial Management is where a project decides how its money will be handled: how costs will be estimated, budgeted and tracked, and how the work will be funded. The result is the financial management plan, which every other process in the Finance domain works from.

What changed in Plan Financial Management: the Sixth Edition's Plan Cost Management compared with the Eighth Edition
Plan Cost Management in the Sixth Edition, Plan Financial Management in the Eighth: the main changes at a glance. The full analysis follows.

What changed

This is Plan Cost Management under a new name, and the new word is broader than the old one. “Cost” covered what the project spends. “Financial” also covers where the money comes from. The Sixth Edition’s cost management knowledge area is now the Finance performance domain, and this process is the first of its four.

The plan it produces was renamed to match. The cost management plan is now the financial management plan, and later processes in the domain take it as an input under that name.

A second output: the funding strategy

The previous set listed one output for this process. The Eighth Edition lists two: the financial management plan and a funding strategy. Funding was already part of cost work in the Sixth Edition, in Determine Budget’s funding requirements and funding limit reconciliation. What is new is that the strategy for funding the project is set here, at planning time, before the budget is built.

The input list also grew from four entries to five, with project documents added. The tools are the same three as before: expert judgment, data analysis (alternatives analysis), and meetings.

If you learned the previous set

The planning job is the one you already know: deciding, before any estimate is made, how the project’s money will be estimated, budgeted and controlled. What needs updating is the name of the process, the name of the plan, and the idea that deciding how the project will be paid for belongs in the same planning step.

Inputs, Tools & Techniques, and Outputs

Compared with the Sixth Edition’s Plan Cost Management. Items marked New, Renamed or Moved changed; everything else carries over.

Inputs 5

  • Project charter
  • Project management plan
  • Project documents New
  • Enterprise environmental factors
  • Organizational process assets

Tools & Techniques 3

  • Expert judgment
  • Data analysis
  • Meetings

Outputs 2

  • Financial management plan RenamedWas the cost management plan
  • Funding strategy New

Every ITTO column in the eighth edition ends in “Etc.”, so the guide presents these lists as typical, not complete. Grouped items such as project documents are shown at the top level. PMBOK® Guide — Eighth Edition, §2.4.2.1. What changed in the ITTOs, across all 40 processes.