Process 21 of 40 — PMBOK 8

Develop Budget

What Determine Budget became in PMBOK 8: a new verb, the same cost baseline, and the one input that was renamed.

Performance Domain Finance Focus Area Planning

Develop Budget is the process that adds up the cost estimates into an authorized cost baseline, and works out how much funding the project needs and when. The cost baseline is what spending will be measured against for the rest of the project.

What changed in Develop Budget: the Sixth Edition's Determine Budget compared with the Eighth Edition
Determine Budget in the Sixth Edition, Develop Budget in the Eighth: the main changes at a glance. The full analysis follows.

What changed

This is Determine Budget under a new name, and it is one of the least changed processes in the Eighth Edition. The input, tool and output counts are the same as before: six, six and three. The tools are the same six: expert judgment, cost aggregation, data analysis (reserve analysis), historical information review, funding limit reconciliation and financing.

The one renamed input follows from the change in Plan Financial Management. The cost management plan is gone, and the financial management plan now feeds this process instead, alongside the resource management plan and the scope baseline.

Where it sits in the Finance domain

The Finance domain has four processes: Plan Financial Management, Estimate Costs, Develop Budget and Monitor and Control Finances. Estimate Costs kept its name and its job, so the order of work is the familiar one. Estimate Costs produces the cost estimates and the basis of estimates, and this process aggregates them into the baseline.

The outputs are the cost baseline, the project funding requirements, and updates to project documents.

If you learned the previous set

Everything you studied still applies: the cost baseline includes contingency reserves but not management reserves, the project budget adds the management reserves on top, and funding limit reconciliation can force work to be rescheduled to fit when money is available. The change you need to remember is the verb. “Determine Budget” is now “Develop Budget”.

Inputs, Tools & Techniques, and Outputs

Compared with the Sixth Edition’s Determine Budget. Items marked New, Renamed or Moved changed; everything else carries over.

Inputs 6

  • Project management plan
  • Project documents
  • Business documents
  • Agreements
  • Enterprise environmental factors
  • Organizational process assets

Tools & Techniques 6

  • Expert judgment
  • Cost aggregation
  • Data analysis
  • Historical information review
  • Funding limit reconciliation
  • Financing

Outputs 3

  • Cost baseline
  • Project funding requirements
  • Project document updates

Every ITTO column in the eighth edition ends in “Etc.”, so the guide presents these lists as typical, not complete. Grouped items such as project documents are shown at the top level. PMBOK® Guide — Eighth Edition, §2.4.2.3. What changed in the ITTOs, across all 40 processes.