Type in four numbers from your project, or from an exam question, and the calculator works out every earned value measure the PMP exam uses. Each result shows its formula with your numbers in it, and says in plain words what the result means. Nothing you type leaves your browser.
The four numbers you need
- Budget at completion (BAC): the total approved budget for the work.
- Planned value (PV): the budgeted cost of the work that was scheduled to be done by today.
- Earned value (EV): the budgeted cost of the work that has actually been done by today.
- Actual cost (AC): what the work done so far has actually cost.
The fifth box is optional. If the remaining work has been re-estimated from the bottom up, enter that estimate and the calculator adds the fourth EAC formula.
Which EAC formula to use
There is no single estimate at completion. Each formula makes a different assumption about the work that is still to come, and an exam question usually tells you which assumption applies.
| If the question says, or implies | Use |
|---|---|
| The variances so far are typical of the rest of the work. This is the default when nothing else is said. | EAC = BAC ÷ CPI |
| The variance was a one-off, and the remaining work will be done at the budgeted rate. | EAC = AC + (BAC − EV) |
| Both cost and schedule performance will affect the remaining work, for example because the end date cannot move. | EAC = AC + (BAC − EV) ÷ (CPI × SPI) |
| The original estimate is no longer believable, and the remaining work has been re-estimated. | EAC = AC + bottom-up ETC |
Estimate to complete (ETC) is then EAC − AC, and variance at completion (VAC) is BAC − EAC.
Two versions of TCPI
The to-complete performance index answers one question: how efficiently does the remaining work have to be done to hit a target? The target can be the original budget or the new forecast, so there are two versions.
- Against the budget: TCPI = (BAC − EV) ÷ (BAC − AC). A result above 1 means the rest of the work has to be done more efficiently than planned.
- Against the forecast: TCPI = (BAC − EV) ÷ (EAC − AC). Use this once the original budget is no longer the target and an EAC has been approved.
The useful comparison is TCPI against the CPI achieved so far. If the TCPI needed is well above the current CPI, finishing on budget would take a large, sudden improvement in performance, and that is rarely realistic.
A worked example
The calculator opens with a small project: a budget of 100,000, planned value of 50,000, earned value of 40,000 and actual cost of 45,000.
- CV = 40,000 − 45,000 = −5,000, and CPI = 40,000 ÷ 45,000 = 0.89. The project is over budget: each 1 spent has earned 0.89 of planned work.
- SV = 40,000 − 50,000 = −10,000, and SPI = 40,000 ÷ 50,000 = 0.80. It is behind schedule, with work getting done at 80% of the planned rate.
- If the cost performance so far continues, EAC = 100,000 ÷ 0.889 = 112,500, so VAC = −12,500. The calculator keeps the CPI unrounded; dividing by the rounded 0.89 gives 112,360, a difference that can matter when an exam’s answer choices are close together.
- To still finish on the original budget, TCPI = 60,000 ÷ 55,000 = 1.09. That is well above the 0.89 achieved so far.
For an exam-style reading: the project is over budget and behind schedule, and finishing on the original budget would need a much better performance than the team has shown so far.
Where earned value sits in PMBOK
In the Sixth Edition, earned value analysis and the to-complete performance index are tools of Control Costs. In the Eighth Edition, they are tools of Monitor and Control Finances, the renamed process.
The cost baseline that earned value is measured against is set earlier, in Determine Budget in the Sixth Edition and in Develop Budget in the Eighth.