Where this came from
This process did not exist under this name before the Eighth Edition. Here is what it was called, and where the previous write-up still lives:
Assess and Implement Changes is the process every change request goes through: it is reviewed, its impact on scope, schedule, cost and risk is weighed, and it is approved, deferred or rejected. Approved changes then flow into the plan and the project documents.
What changed
This is Perform Integrated Change Control under a new name. The new name says what the process actually does, assess a change and then put it into effect, where the old one named the mechanism. The mechanism has not gone away. Integrated change control is now listed as a tool of this process, so the old process name lives on as one of its techniques.
Inputs and outputs are essentially unchanged. Change requests and work performance reports come in; approved change requests and plan and document updates go out.
Predictive and adaptive projects are treated separately
The guide describes this process twice: once for predictive projects and once for adaptive ones. On a predictive project, change runs through formal change control, usually with a change control board and updates to the baselines. On an adaptive project, most change is expected and is absorbed through the backlog. That is why backlog management now appears in the tools list, next to change control tools and integrated change control.
If you learned the previous set
The core rules hold: no change to a baseline without approval, and every change assessed for its effect across the whole project, not just the part it touches. The difference is that “put it in the backlog and let the product owner prioritize it” is now a correct answer to a change question on an adaptive project, not a shortcut around the process.
Inputs, Tools & Techniques, and Outputs
Compared with the Sixth Edition’s Perform Integrated Change Control. Items marked New, Renamed or Moved changed; everything else carries over.
Inputs 6
- Project management plan
- Project documents
- Work performance reports
- Change requests
- Enterprise environmental factors
- Organizational process assets
Tools & Techniques 7
- Expert judgment
- Change control tools
- Data analysis
- Decision-making
- Meetings
- Integrated change control New
- Backlog management New
Outputs 3
- Approved change requests
- Project management plan updates
- Project document updates
Every ITTO column in the eighth edition ends in “Etc.”, so the guide presents these lists as typical, not complete. Grouped items such as project documents are shown at the top level. PMBOK® Guide — Eighth Edition, §2.1.6.8. What changed in the ITTOs, across all 40 processes.