Process 11 of 49

Estimate Activity Durations

Estimates how long each activity will take given the resources assigned, producing duration estimates and the basis behind them. These durations are the raw material the schedule is built from.

Process Group Planning Knowledge Area Project Schedule Management

This process estimates the number of work periods each activity needs, based on scope, resource requirements, and historical data. The team chooses estimating techniques — analogous, parametric, three-point, bottom-up — and records not just the numbers but the basis of estimates, so the assumptions behind them stay visible.

Estimate Activity Durations: key inputs and outputs
The key inputs feeding Estimate Activity Durations and the deliverables it produces — full ITTOs are listed below.

Good estimates express uncertainty as a range rather than a single point, and reserve analysis sets aside contingency for known risks. The PM avoids treating an estimate as a commitment until it has been validated against resources and dependencies.

Common pitfalls. Single-point estimates that hide uncertainty; padding buried inside estimates instead of explicit reserves; ignoring resource availability and productivity; and reusing analogous estimates from genuinely different work.

Inputs, Tools & Techniques, and Outputs

Inputs

  • Project management plan
  • Project documents
  • Enterprise environmental factors
  • Organizational process assets

Tools & Techniques

  • Expert judgment
  • Analogous estimating
  • Parametric estimating
  • Three-point estimating
  • Bottom-up estimating
  • Data analysis
  • Decision making
  • Meetings

Outputs

  • Duration estimates
  • Basis of estimates
  • Project documents updates

← All PMBOK Processes